June 2020 Construction Update

Owen-Ames-Kimball Co.

Updated: Mar 24, 2021

Construction is well underway at multiple schools within the district after the stay-at-home order was lifted for the construction industry.


Baldwin Street Middle School

At Baldwin St. Middle School, the existing roof is being removed and replaced. Additionally, there will be alterations to the roof and over flow drains. By the end of the month, the production re-roofing work will be well passed halfway.

Roof Area 14 looking north with new roof membrane
Roof Area 14 looking south with new roof membrane

Forest Grove Elementary School

At Forest Grove Elementary, the drop-off and parking lot will be expanded/reconfigured, and the bus loop will be getting new asphalt. Site clearing and asphalt removal are well underway

Looking south at existing bus loop with asphalt removed
East facing view of the former parent drop-off with asphalt removed and site clearing underway

Upcoming Projects

The design meetings for upcoming projects, including the high school additions and new 5/6 building, are progressing virtually! It will be nice when we can be face-to-face again.

Just a small sneak peak of the ongoing design meeting for the new 5/6 building starting next year

 
 
 

Recent Posts

See All

Comments


GMB Logo.png

ARCHITECTUrAL PARTNER

GMB is a full service A/E firm, and serves as the architectural partner for Hudsonville Public Schools.

SUBSCRIBE VIA EMAIL

4H3A4517.jpg

CONSTRUCTION

TIMELINE

Construction projects began in 2020 and will span the course of six years.

O-A-K Logo, Website Navy, Square.png

BROUGHT TO YOU BY O-A-K

Owen-Ames-Kimball Co. is our construction management partner for all construction projects.

Thanks for submitting!

© 2021 by Owen-Ames-Kimball Co., Grand Rapids, Michigan

bottom of page